Productivity
Machine cycle time = 10 seconds for all sizes
Load time = 5 seconds (dependent upon speed of operator)
Complete Take-Offs:
4 per minute
240 per hour
1,920 per 8 hour shift
480,000 per year (1 shift/day; 5 days/week; 50 weeks/year)
Assuming labor cost of one operator = $25,000/year, one take-Off = 5.2¢ labor to produce